Monroe Street Project

By Staff | Oct 27, 2011

Work continues at a steady pace on the Monroe Street Project. Pictured at the corner of 7th and Monroe, a maintainer is doing subgrade preparation for asphalt application. Asphalt will go down early next week. Curb and gutter is finished from 5th to 8th Streets on Monroe. Crews are working on sanitary sewer services on 11th Street. Intakes to storm sewer at the intersection of 11th and Des Moines and the intersection of 11th and Jefferson are being worked on before the curb and gutter crew moves in. “If we have a few good weeks with little or no precipitation, we’ll get a lot done,” said Public Works Director Bill Dickey. --Jane Whitmore photo