New Curb and Gutter

By Staff | Oct 18, 2011

Curb and gutter and blacktop surfacing continues on the Monroe Steet project. Here is a progress report: Curb and gutter is being poured on Monroe between 5th and 8th Streets. Blacktop surfacing is finished on 10th Street and 12th Street. Work on underground utilities will begin on 11th Street between Monroe and Jefferson. --JWhitmore photo